The overall objective of this project was to support Serbia in reforming the energy policy by meeting EU Acquis through enhanced strategic planning, increase use of renewable energy and infrastructure support for establishing a regional energy market, and improvement of water quality in Sava river by decreasing the concentration of relevant parameters at the WWTP outlet (mineral oils, suspended solids, heavy metals, etc) leading to an improvement in water quality around the thermal power plant (TPP), thus enabling the health of overall population to improve.
The specific objective of this framework contract is to provide EPS/TPP Nikola Tesla with the necessary assistance in the coordination, supervision, and project and site management of Design- Build contract for construction under FIDIC rules: Design, construction, trial operation and commissioning of Waste Water Treatment Plant at TPP Nikola Tesla A (Plant and Design-Build – Yellow Book). The project provides a Supervising Engineer to be a part of the Project Management Unit (PMU).
Supervising Engineer shall perform supervision during the finalization of project completion and Defects Notification Period, to take part in commissioning and tests, to issue taking-over and performance certificates.